Question: A partially solved PERT problem is detailed in the table below. Times are given in weeks. table [ [ Activity , Preceding,Optimistic Probable Pessimistic

A partially solved PERT problem is detailed in the table below. Times are given in weeks.
\table[[Activity,Preceding,Optimistic Probable Pessimistic Expec,],[A,Time,Time,Time,],[B,A,2,2,8],[C,A,8,12,16],[D,--,3,5,10],[E,C,4,6,8],[F,B,6,8,10],[G,F,2,3,4],[H,D, E,2,2,8],[I,G,6,8,16],[J,H,4,6,14],[K,I, J,2,2,5]]
Which activities form the critical path?
A-B-E-F-J
A-B-E-F-K
A-C-E-H-J-K
B-C-E-H-J-K