Question: A precedence schedule for a project is given below, together with tabulated direct cost data. Indirect (overhead) cost is given as $500 per day. (Note:


A precedence schedule for a project is given below, together with tabulated direct cost data. Indirect (overhead) cost is given as $500 per day. (Note: Read the table in the following manner: activity A can be compressed by one day from three days to two days, etc) You are required to compress the schedule TWICE and determine the outcomes of each compression. Outcomes of the first compression: Compress Activity Revised time = by Days Direct Costs =5 Indirect (Overhead) Costs =$ Outcomes of the second compression: Compress Activity Revised time = Days Direct Costs =$ Indirect (Overhead) Costs =$