Question: ~~ Question Completion Status: QUESTION 3 A precedence schedule for a project is given below, together with tabulated direct cost data. Indirect ( overhead )

~~ Question Completion Status:
QUESTION 3
A precedence schedule for a project is given below, together with tabulated direct cost data. Indirect (overhead) cost is given as $400 per day.