Question: A precedence schedule for a project is given below, together with tabulated direct cost data. Indirect ( 0 verhead ) cost is given as $
A precedence schedule for a project is given below, together with tabulated direct cost data. Indirect verhead cost is given as $ per day.
Note: Read the table in the following manner: activity A can be compressed by one day from three days to two days, etc
You are required to compress the schedule TWICE and determine the outcomes of each compression.
Outcomes of the first compression:
Compress Activity
by
Days
Revised time
Days
Direct Costs $
Indirect Overhead Costs $
Outcomes of the second compression:
Compress Activity
by
Days
Revised time
Days
Direct Costs $
Indirect Overhead Costs $