Question: QUESTION 3 A precedence schedule for a project is given below, together with tabulated direct cost data. Indirect {overhead} cost is given as $500 per

QUESTION 3 A precedence schedule for a project is given below, together with tabulated direct cost data. Indirect {overhead} cost is given as $500 per day. (Note: Read the table in the following manner: activity A can be compressed by one day from three days to two days, etc] You are required to compress the schedule TWICE and determine the outcomes of each compression. Outcomes of the first compression: Compress Activity by Days Revised time = Days Direct Costs = $ Indirect (Overhead) Costs = 5 Outcomes of the second compression: Compress Activity by Days Revised time = Days Direct Costs = 5 Indirect (Overhead) Costs = S