Question: A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 91 days with a project variance of 25, what is the probability that the project will be completed in 88 days or less?
| A. | 0.1587 | |
| B. | 0.4207 | |
| C. | 0.2743 | |
| D. | 0.2119 |