Question: A project being analyzed by PERT has 53 activities, 22 of which are on the critical path. If the estimated time along the critical path
A project being analyzed by PERT has 53 activities, 22 of which are on the critical path. If the estimated time along the critical path is 107 days with a project variance of 23, the probability that the project will be completed in 112 days or less is