Question: A project for improving a billing process has the follow - ing precedence relationships and activity times. Activity Activity Time ( wks ) Immediate Predecessor

A project for improving a billing process has the follow- ing precedence relationships and activity times. Activity Activity Time (wks) Immediate Predecessor(s) A3 B 11 C 7 A D 13 B, C E 10 B F 6 D G 5 E H 8 F, G