Question: A project for improving a billing process has the follow- 3. ing precedence relationships and activity times. Activity Time (wks) Activity Immediate Predecessor(s) A 3

A project for improving a billing process has theA project for improving a billing process has the

A project for improving a billing process has the follow- 3. ing precedence relationships and activity times. Activity Time (wks) Activity Immediate Predecessor(s) A 3 B 11 C 7 A D 13 B, C E 10 B F 6 D 5 E H H 8 F, GT a. Draw the network diagram. b. Calculate the slack for each activity. Which activities are on the critical path