Question: A project for improving a billing process has the follow- ing precedence relationships and activity times. Immediate Predecessor(s) 3. Activity Activity Time (wks) 3 11

A project for improving a billing process has the

A project for improving a billing process has the

A project for improving a billing process has the follow- ing precedence relationships and activity times. Immediate Predecessor(s) 3. Activity Activity Time (wks) 3 11 B 7 C A D 13 B,C E 10 B 6 D F E 5 G H 299 8 F, G a. Draw the network diagram. b. Calculate the slack for each activity. Which activities are on the critical path