Question: A project for improving a billing process has the following precedence relationships and activity times. table [ [ Activity , Activity Time ( wks

A project for improving a billing process has the following precedence relationships and activity times.
\table[[Activity,Activity Time (wks),Immediate Predecessor(s)],[A,3,-],[B,11,-],[C,7,A],[D,13,B, C],[E,10,B],[F,6,D],[G,5,E],[H,8,F, G]]
a. Draw the network diagram.
b. Calculate the slack for each activity. Which activities are on the critical path?
 A project for improving a billing process has the following precedence