Question: A project for improving a billing process has the following precedence relationships and activity times: table [ [ Activity , Activity Time ( weeks

A project for improving a billing process has the following precedence relationships and activity times:
\table[[Activity,Activity Time (weeks),Immediate Predecessor(s)],[A,5,-],[B,12,-],[C,5,A],[D,14,B, C],[E,11,B],[F,5,D],[G,4,E],[H,7,F, G]]
a. Choose the correct network diagram below.
A. B.
c.
D.
F
b. Calculate the slack for each activity. Which activities are on the critical path?
\table[[Activity,\table[[Activity],[Time (weeks)]],\table[[On],[critical path?]],\table[[Slack],[(weeks)]]],[A,5,No,2],[B,12,Yes,0],[C,5,No,2],[D,14,Yes,0],[E,11,No,4],[F,5,Yes,0],[G,4,No,4],[H,7,Yes,0]]
A project for improving a billing process has the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!