Question: A project for improving a billing process has the following precedence relationships and activity times: table [ [ Activity , Activity Time ( weeks

A project for improving a billing process has the following precedence relationships and activity times:
\table[[Activity,Activity Time (weeks),Immediate Predecessor(s)],[A,4,-],[B,12,-],[C,5,A],[D,14,B, C],[E,11,B],[F,4,D],[G,4,E],[H,9,F, G]]
a. Choose the correct network diagram below.
A. B.
(4)
c. D.
a. Choose the correct network diagram below.
A.
B.-
c. D.
(B12)(D14),(G4)
r
D.
b. Calculate the slack for each activity. Which activities are on the critical path?
\table[[Activity,Activity Time (weeks),On critical path?,Slack (weeks)],[A,4,grad,],[B,12,grad,],[C,5,grad,],[D,14,grad,],[E,11,grad,],[F,4,grad,],[G,4,grad,],[H,9,grad,]]
A project for improving a billing process has the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!