Question: A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) A 55 B 99
A project for improving a billing process has the following precedence relationships and activity times:
| Activity | Activity Time (weeks) | Immediate Predecessor(s) |
| A | 55 | |
| B | 99 | |
| C | 55 | A |
| D | 1414 | B, C |
| E | 1111 | B |
| F | 55 | D |
| G | 44 | E |
| H | 99 | F, G |
a. Choose the correct network diagram below.

b. Calculate the slack for each activity. Which activities are on the critical path?
| Activity Time(daydays) | Start (daydays) | Finish (daydays) | Critical Path | Slack (daydays) | |||
| Activity | Earliest | Latest | Earliest | Latest | |||
| A |
|
|
|
|
|
|
|
| B |
|
|
|
|
|
|
|
| C |
|
|
|
|
|
|
|
| D |
|
|
|
|
|
|
|
| E |
|
|
|
|
|
|
|
| F |
|
|
|
|
|
|
|
| G |
|
|
|
|
|
| |