Question: A project for improving a billing process has the following precedence relationships and activity times. Activity Activity Time (wks) Immediate Predecessor(s) A 3 - B
A project for improving a billing process has the following precedence relationships and activity times.
| Activity | Activity Time (wks) | Immediate Predecessor(s) |
| A | 3 | - |
| B | 11 | - |
| C | 7 | A |
| D | 13 | B, C |
| E | 10 | B |
| F | 6 | D |
| G | 5 | E |
| H | 8 | F, G |
A) Draw the network diagram.
B) Calculate the slack for each activity. Which activities are on the critical path?