Question: A project for improving a billing process has the following precedence relationships and activity times. Activity Activity Time (wks) Immediate Predecessor(s) A 3 - B

A project for improving a billing process has the following precedence relationships and activity times.

ActivityActivity Time (wks)Immediate Predecessor(s)
A3-
B11-
C7A
D13B, C
E10B
F6D
G5E
H8F, G

A) Draw the network diagram.

B) Calculate the slack for each activity. Which activities are on the critical path?