Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start AB A 0.38 E 1 D 41 0.36

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start AB A 0.38 E 1 D 41 0.36 End 15 3.26 E End 10 0 113 88 D What is the probability that the project will be completed within 177 days? a. 0.25 Cb. 0.18 . d. 0.82 Ce 1

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!