Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A 72 0.24 B E 60

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A 72 0.24 B E 60 1 D 24 0.24 D End 32 3.52 End 23 0 What is the probability that the project will be completed within 136 days? a. 1 b. 0.25 c. 0 d. 0.82 e. 0.18