Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start AB 18 0.23 B E 10 0.25 C

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start AB 18 0.23 B E 10 0.25 C D 45 0.2 D End 11 0.57 E End 10 0.75 What is the probability that the project will be completed within 78 days? O a 0.82 Ob. 0.18 Oc 0.25 od 0 O e 1