Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B 1 A C 40 0.24 B

A project has five activities with the durations
A project has five activities with the durations
A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B 1 A C 40 0.24 B E 36 1 C D 12 0.23 D End 49 3.53 E End 48 0 What is the probability that the project will be completed within 109 days? O a. 0.18 O b. 0.82 O c. 0.25 O d. 1 O e. 0