Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A C 71 0.29 B E

A project has five activities with the durations
A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A C 71 0.29 B E 55 1 C D 21 0.2 D End 15 3.51 E End 12 0 What is the probability that the project will be completed within 115 days? a. 0.25 O b. 1 Oc. 0 O d. 0.82 e. 0.18