Question: A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A C 40 0.24 E 36

A project has five activities with the durations

A project has five activities with the durations (days) listed below: Activity Precedes Expected Variance Duration Start A, B A C 40 0.24 E 36 1 D 12 0.23 End 49 3.53 End 48 0 What is the probability that the project will be completed within 109 days? O a. 0 O b. 0.18 O c. 0.25 O d. 0.82 O e. 1 E U