Question: A project has four activities ( A , B , C , and D ) that must be performed sequentially. The prob - ability distributions

A project has four activities (A, B, C, and D) that must be performed sequentially. The prob- ability distributions for the time required to complete each of the activities are as follows: SELF test ActivityActivity Time(weeks) ProbabilityA 50.2560.3570.2580.15B 30.2050.5570.25C 100.10120.25140.40160.20180.05