Question: A project is behind schedule because the contractor has been working on other projects. The subcontractors have been acting unprofessionally and have offended other employees
A project is behind schedule because the contractor has been working on other projects. The subcontractors have been acting unprofessionally and have offended other employees outside the project. The project charter was not clearly defined during initiation. The stakeholders are frustrated at the low quality of some of the deliverables. Which of the following should be done FIRST to address these issues?
A.Trigger the incident response plan and notify the contractor.
A.
Trigger the incident response plan and notify the contractor.
B.Plan a team-building exercise for the project team and contractor.
B.
Plan a team-building exercise for the project team and contractor.
C.Hold a meeting with the contractor and review the issue log and contract.
C.
Hold a meeting with the contractor and review the issue log and contract.
D.Ask staff to review the communication plan and code of conduct.
D.
Ask staff to review the communication plan and code of conduct.