Question: A project is found to have expected time T = 35.1 days and variance V = 3.23. What value of z is needed to find
A project is found to have expected time T = 35.1 days and variance V = 3.23. What value of z is needed to find the probability that the project will take at least 40 days? (round final answer to 2 decimals as needed)
Select one:
a. 2.73
b. 20.47
c. 1.52
d. -2.73
e. -12.84
f. 29.13
g. -1.52