Question: A project is found to have expected time T = 35.1 days and variance V = 3.23. What value of z is needed to find

A project is found to have expected time T = 35.1 days and variance V = 3.23. What value of z is needed to find the probability that the project will take at least 40 days? (round final answer to 2 decimals as needed)

Select one:

a. 2.73

b. 20.47

c. 1.52

d. -2.73

e. -12.84

f. 29.13

g. -1.52