Question: A project is found to have expected time T = 35.8 days and variance V = 3.25. What value of z is needed to find

A project is found to have expected time T = 35.8

A project is found to have expected time T = 35.8 days and variance V = 3.25. What value of z is needed to find the probability that the project will take at most 30 days? (round final answer to 2 decimals as needed) Select one: O a. 1.78 O b.-3.22 OC.-19.16 O d. 18.98 Oe. -1.78 Of. 10.14 O g. 3.22 Check