Question: Please show all work! 8. A project is found to have expected time T = 35.33 days and variance V = 3.22. What value of

Please show all work! 8. A project is found to

Please show all work! 8. A project is found to

Please show all work!

8. A project is found to have expected time T = 35.33 days and variance V = 3.22. What value of z is needed to find the probability that the project will take at least 40 days? (round final answer to 2 decimals as needed) b. What value of z is needed to find the probability that the project will take at most 40 days? (round final answer to 2 decimals as needed) c. What value of z is needed to find the probability that the project will take at most 30 days? (round final answer to 2 decimals as needed) d. Which of the following is a correct way to calculate P{32 st

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!