Question: A project is found to have expected time T = 35.8 days and variance V = 3.17. What value of z is needed to find

A project is found to have expected time T = 35.8 days and variance V = 3.17. What value of z is needed to find the probability that the project will take at least 40 days? (round final answer to 2 decimals as needed)

Select one:

a. 28.71

b. -13.33

c. 19.89

d. -2.36

e. 2.36