Question: A project is found to have expected time T = 35.8 days and variance V = 3.17. What value of z is needed to find
A project is found to have expected time T = 35.8 days and variance V = 3.17. What value of z is needed to find the probability that the project will take at least 40 days? (round final answer to 2 decimals as needed)
Select one:
a. 28.71
b. -13.33
c. 19.89
d. -2.36
e. 2.36
f. 1.32
g. -1.32