Question: A project is found to have expected time T = 35.7 days and variance V = 3.13. What value of z is needed to find

A project is found to have expected time T = 35.7
A project is found to have expected time T = 35.7 days and variance V = 3.13. What value of z is needed to find the probability that the project will take at most 40 days? (round final answer to 2 decimals as needed) Select one: O a.-1.37 O b.-2.43 O c. 28.59 O d. 19.82 O e.-13.09 O f. 1.37 Og. 2.43 Check