Question: A project manager has decided to use probabilistic time estimates. She has put the time estimates for path A-B-C into this table: Task t o
A project manager has decided to use probabilistic time estimates. She has put the time estimates for path A-B-C into this table:
| Task |
|
|
| |||
| A | 15 | 23 | 25 | |||
| B | 1 | 3 | 7 | |||
| C | 12 | 14 | 22 |
a) What is the formula for the estimated time for task A
b) What is the estimated time for Tack C?
c) What is the estimated duration of path A-B-C?