Question: A project network has the 4 paths from the Start to the End and their lengths are as follows. Path 1 = 35 days, Path

A project network has the 4 paths from the Start

A project network has the 4 paths from the Start to the End and their lengths are as follows. Path 1 = 35 days, Path 2 = 40 days, Path 3 = 32 days, Path 4 = 38 days. What is the probability of completing this project in 45 days of variance of the critical path (Vcp) is 20.54? 0.805 0.825 0.865 0.845