Question: A project network has the 4 paths from the Start to the End and their lengths are as follows. Path 1 = 30 days, Path
A project network has the 4 paths from the Start to the End and their lengths are as follows. Path 1 = 30 days, Path 2 = 35 days, Path 3 = 27 days, Path 4 = 33 days. What is the probability of completing this project in 40 days of variance of the critical path (Vcp) is 12.98? A. 0.937 B. 0.917 C. 0.897 D. 0.957