Question: A project network has the 4 paths from the Start to the End and their lengths are as follows. Path 1 = 25 days, Path

A project network has the 4 paths from the Start to the End and their lengths are as follows. Path 1 = 25 days, Path 2 = 30 days, Path 3 = 22 days, Path 4 = 28 days.

What is the probability of completing this project in 34 days of variance of the critical path (Vcp) is 10.08?

0.936

0.896

0.916

0.956