Question: A project network has the 4 paths from the Start to the End and their lengths are as follows. Path 1 = 20 days, Path

A project network has the 4 paths from the Start

A project network has the 4 paths from the Start to the End and their lengths are as follows. Path 1 = 20 days, Path 2 = 25 days, Path 3 = 17 days, Path 4 = 23 days. What is the probability of completing this project in 28 days of variance of the critical path (Vcp) is 11.88? 0.828 0.768 0.808 0.788