Question: A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to complete the

A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to complete the task.

Task

Duration

Depends on

T1

1

T2

3

T3

5

T4

3

T1

T5

2

T1

T6

2

T1,T3

T7

1

T2,T3

T8

3

T4,T5,T6

T9

3

T5,T7

T10

2

T7

T11

2

T8

T12

3

T8,T9

T13

2

T10

answer the questions below. These activities are intended to develop and assess your understanding of the method, so please do not use a software project management tool such as Microsoft Project to assist in either drawing the diagrams or in computing solutions.

Questions :

Assume one person works on each task(That is : use the duration in the task list table) answer the following :

=> List or otherwise indicate the task on the critical path and compute its length,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Databases Questions!