Question: Project Scheduling A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to
Project Scheduling A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to complete the task.
| Task | Duration | Depends on |
| T1 | 1 | |
| T2 | 3 | |
| T3 | 5 | |
| T4 | 3 | T1 |
| T5 | 2 | T1 |
| T6 | 2 | T1,T3 |
| T7 | 1 | T2,T3 |
| T8 | 3 | T4,T5,T6 |
| T9 | 3 | T5,T7 |
| T10 | 2 | T7 |
| T11 | 2 | T8 |
| T12 | 3 | T8,T9 |
| T13 | 2 | T10 |
answer the questions below. These activities are intended to develop and assess your understanding of the method, so please do not use a software project management tool such as Microsoft Project to assist in either drawing the diagrams or in computing solutions.
Questions :
A)
=> draw an activity network. Show a start and finish "Activity" (These are zero length pseudo-activities),
=> List or otherwise indicate the task on the critical path and compute its length,
=>For each non-critical task , how many weeks may its strat be delayed without affecting the finish time of the project