Question: A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to complete the
A project requires the tasks shown below to be completed. The duration column shows the number of weeks estimated for one person to complete the task.
| Task | Duration | Depends on |
| T1 | 1 | |
| T2 | 3 | |
| T3 | 5 | |
| T4 | 3 | T1 |
| T5 | 2 | T1 |
| T6 | 2 | T1,T3 |
| T7 | 1 | T2,T3 |
| T8 | 3 | T4,T5,T6 |
| T9 | 3 | T5,T7 |
| T10 | 2 | T7 |
| T11 | 2 | T8 |
| T12 | 3 | T8,T9 |
| T13 | 2 | T10 |
answer the questions below. These activities are intended to develop and assess your understanding of the method, so please do not use a software project management tool such as Microsoft Project to assist in either drawing the diagrams or in computing solutions.
Questions :
Assume one person works on each task(That is : use the duration in the task list table) answer the following :
=> draw the Gantt chart, showing the earliest start and finishing time for each task.
Step by Step Solution