Question: A project scheduler provides a status report that indicates a schedule variance of -$2500. Which of the following does that mean? The project is over
A project scheduler provides a status report that indicates a schedule variance of -$2500.
Which of the following does that mean?
- The project is over budget by $2500 worth of work.
- The project has saved $2500 worth of work.
- The project has accomplished $2500 worth of work.
- The project is behind schedule by $2500 worth of work.
Two highly skilled resources, who are currently working on other project, are assigned to a project manager.
Personality conflicts between the two resources have adversely affect~~~~~~~~~
Provide input to resolve the issue, but the project manager does not have the level of authority required to resolve the personality conflict. Which of the following structure types is~~~~
- Strong matrix
- Balanced matrix
- Functional
- Weak Matrix
- Projectized