Question: A project starting this summer has the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic start A,B - - -

A project starting this summer has the following work breakdown structure:

Time Estimates (days)

Activity Precedes Optimistic Most Likely Pessimistic
start A,B - - -
A C,D 44 50 56
B D 45 60 75
C E 42 45 48
D F 31 40 49
E F 27 36 39
F end 58 70 82

What is the probability that this project will be completed within 155 days? It would be helpful to draw a network first.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!