Question: A project starting this summer has the following work breakdown structure: Time Estimates (days) Activity Precedes Optimistic Most Likely Pessimistic start A,B - - -
A project starting this summer has the following work breakdown structure:
Time Estimates (days)
| Activity | Precedes | Optimistic | Most Likely | Pessimistic |
|---|---|---|---|---|
| start | A,B | - | - | - |
| A | C,D | 44 | 50 | 56 |
| B | D | 45 | 60 | 75 |
| C | E | 42 | 45 | 48 |
| D | F | 31 | 40 | 49 |
| E | F | 27 | 36 | 39 |
| F | end | 58 | 70 | 82 |
What is the probability that this project will be completed within 155 days? It would be helpful to draw a network first.