Question: A project was planned using PERT. Its expected completion time was determined to be 8 5 days. The variance of the critical path is 4

A project was planned using PERT. Its expected completion time was determined to be 85 days. The variance of the critical path is 49. What is the probability the project will be completed within 75 days (5 decimal places)? Let X = the project completion time.