Question: A project was planned using PERT. Its expected completion time was determined to be 66 weeks. The standard deviation of the critical path is 7.
A project was planned using PERT. Its expected completion time was determined to be 66 weeks. The standard deviation of the critical path is 7. What is the probability (rounding to 5 decimal places) that the project will be finished in 60 weeks or more. Let X = the project completion time.
P(X _____) = _________________________________________________________________________________________________________________________ Please show how you use the Normal Curve Table to obtain your answer in the space below.