Question: A short project is defined by activities with three time estimates ( in days ) as shown in the table. table [ [ Activity
A short project is defined by activities with three time estimates in days as shown in the table.
tableActivityOptimistic,Most Likely,Pessimistic,PredecessorABCA BDBEDFC
What is the variance of activity
a
b
c
d