Question: A short project is defined by activities with three time estimates ( in days ) as shown in the table. table [ [ Activity

A short project is defined by activities with three time estimates (in days) as shown in the table.
\table[[Activity,Optimistic,Most Likely,Pessimistic,Predecessor],[A,4,6,8,],[B,5,9,13,],[C,10,12,15,A, B],[D,9,12,16,B],[E,6,9,15,D],[F,10,13,18,C]]
What is the expected duration of this project?
a.35.5 days
b.32.5 days
c.34.5 days
d.33.5 days
 A short project is defined by activities with three time estimates