Question: A short project is defined by activities with three time estimates ( in days ) as shown in the table. table [ [ Activity

A short project is defined by activities with three time estimates (in days) as shown in the table.
\table[[Activity,Optimistic,Most Likely,Pessimistic,Predeces],[A,4,6,8,],[B,5,9,13,],[C,10,12,15,A, B],[D,9,12,16,B],[E,6,9,15,D],[F,10,13,18,C]]
What is the probability that the project will be completed in less than 32 days?
a.0.19
b.0.11
c.0.07
d.0.15
 A short project is defined by activities with three time estimates

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!