Question: A short project is defined by activities with three time estimates ( in days ) as shown in the table.Activity Optimistic Most Likely Pessimistic Predecessor
A short project is defined by activities with three time estimates in days as shown in the table.Activity Optimistic Most Likely Pessimistic PredecessorU OA BBDFWhat is the probability that the project will take longer than days to complete?