Question: A short project is defined by activities with three time estimates ( in days ) as shown in the table.Activity Optimistic Most Likely Pessimistic Predecessor

A short project is defined by activities with three time estimates (in days) as shown in the table.Activity Optimistic Most Likely Pessimistic Predecessor4685913U O10121591216A, BB6915DF101318What is the probability that the project will take longer than 36 days to complete?