Question: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate

A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8. Select one: a. The network has no critical path. b. The critical path is A-C, duration 12. c. The critical path is A-B-C, duration 15. d. The critical path is A-B-C, duration 13.5 e. The critical path cannot be determined without knowing expected activity times.

select any one of the statement fit to the given scenario in question

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!