Question: A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate
A simple CPM network has three activities, A, B, and C. A is an immediate predecessor of B and of C. B is an immediate predecessor of C. The activity durations are A=4, B=3, C=8. Select one: a. The network has no critical path. b. The critical path is A-C, duration 12. c. The critical path is A-B-C, duration 15. d. The critical path is A-B-C, duration 13.5 e. The critical path cannot be determined without knowing expected activity times.
select any one of the statement fit to the given scenario in question
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts