Question: A simple path network has three activities. A,B and C.A is immdieate predecessor of B and of C, B is immediate predecessor of C.The activity

A simple path network has three activities. A,B and C.A is immdieate predecessor of B and of C, B is immediate predecessor of C.The activity duration are A=4, B=3 and C = 8.

Duration proejct =