Question: A task was timed for 60 cycles. It took an average of 118 minutes per cycle. The performance rating was 85 percent, and workday allowance

A task was timed for 60 cycles. It took an
A task was timed for 60 cycles. It took an average of 118 minutes per cycle. The performance rating was 85 percent, and workday allowance is 8 percent Determine each of the following (Do not round intermediate calculations. Round the final answers to 2 decimal places.) a. Observed time. b. Normal time. C. Standard time. minutes minutes minutes