Question: a) Total Project Time b) Critical activities c) Critical Path d) Float Activities and days ACTIVITY TABLE Activity Predecessor Duration (days) A 5 B A

a) Total Project Time b) Critical activities c)

a) Total Project Time b) Critical activities c) Critical Path d) Float Activities and days ACTIVITY TABLE Activity Predecessor Duration (days) A 5 B A 8 C A 4 D B,C 4 E D 14 T1 D 8 G E 1 H E.F 7 I G.H