Question: Act Predecessor Optimistic Most likely Pessimistic a - 15 8 25 b - 15 8 20 c a, b 6 10 12 d c 18

Act Predecessor Optimistic Most likely Pessimistic a - 15 8 25 b - 15 8 20 c a, b 6 10 12 d c 18 24 26 e d 13 19 25 f d 12 18 23 g d 15 17 19 h fg 22 25 30 i e,h 11 15 17

4.1 Using the PERT formula calculate the time for each activity

4.2 Calculate the variance for each activity.

4.3 Construct the network diagram (Activity on Node)

4.4 Identify the critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!