Question: Activity Predecessor Optimistic Most likely Peimis A 15 8 25 B 15 8 20 C A,b 6 10 12 D C,D 18 24 26 E

Activity Predecessor Optimistic Most likely Peimis
A 15 8 25
B 15 8 20
C A,b 6 10 12
D C,D 18 24 26
E d 13 19 25
F d 12 18 23
G d 15 17 19
H f,g 22 25 30
I e,h 11 15 17

1.1 using pert formula calculate the time for each activity.

2.2 calculate the variance.

2.3 construct a net work diagram.

4.4 identify the critical path.